In the first few days we've set up the "batter boards" and set the outside forms for the footings level and square.
The batter boards hold up string lines (which I've highlighted in yellow in the picture) which we use to establish the placement of the formwork below.
Monday there will be five of us working on site as my brother, Ryan is flying in tonight for the week, and my dad will be there with his two workers Mike and Jake. We should get lots done and hopefully pour the concrete by the end of this week. Hopefully it'll warm up enough...